- Contractor: Bruner Corporation
- Engineer: EYP
- Architect: Corgan
- Project Size: 300,000 sq. ft.
- Construction Schedule: 14 months
- Completion Date: September 2007
Bruner Corporation was selected as a partner on this unique,
fast tracked 300,000 square foot Data Center project. Extensive
pre-planning and fabrication were necessary in order to make
this a successful project. 13,000 hours of the total 75,000 were
performed by the Bruner Fabrication Shop. The underground
plumbing began in July of 2006 and was completed in
October of 2006. Mechanical piping began in January
of 2007. In May of 2007 chilled water circulation began.
The cooling system included (6) 1,000 ton chillers, (8)
1,000 gpm horizontal split case primary chilled water
pumps, (8) 1,000 gpm horizontal split case secondary
chilled water pumps, (14) 1,500 gpm vertical turbine
condenser water pumps, (2) 1,000 ton plate and
frame heat exchangers, (13) air handling units, (97)
computer room air handlers and (8) battery exhaust
systems. The emergency power system consist of
(8) 2,000 kw generators, 30” generator exhaust
with SCR scrubber system, (8) urea feed systems,
(4) 30,000 gallon underground fuel oil storage
tanks, (12) 400 gallon day tanks, (2) fuel oil
control systems and (2) waste oil systems.
|