Project included the installation of 3 centrifugal chillers and cooling towers and pumps for this critical Bank One Data Center. Extensive estimating and engineering was needed to develop a plan to install and commission the mechanical systems while the Data Center remained in operation. Detailed scheduling, preplanning, pipe fabrication and strong attention to quality control was key to the success of the entire project.


Bank One

Contractor: Bruner Corporation

Engineer: HAWA

Architect: HAWA

Project Size: Mechanical Room

Construction Schedule: 9 Months

Completion Date: May 2004

 

 