Project involved the upgrade and expansion
of a 20 year-old operating data center to current technology
for “mission critical” operation, to assure
that this facilities’ operation would not be interrupted.
This included replacing existing 1000 ton capacity cooling
towers, pumps, piping and controls in a (3) phase process.
40 pipe-fi tters worked a 12-hour shutdown to complete
60 tie-ins to existing piping in the data processing area.
Bruner worked closely with the owner, engineer, and other
contractors to identify equipment and systems critical
to the immediate criteria for a Tier 4 system.